| Pre-Construction Activity |
| Tendering | Section | Activity | Successful Bid /Cost | Contractor | Award |
| Reach-6/2016/Demolition/DLN-7/03 | Kalena Agrahara to Tavarekere | Demolition | crore (US$91,000) | B R Chawla Demolition | 13 Jul 2016 |
| Reach-6(UG)/2017/Demolition/DLN-8/20 | Tavarekere to Nagawara | Demolition | crore (US$210,000) | B R Chawla Demolition | 15 May 2017 |
| CEE-1/ELE-US/R-6/PH-II/DPO/2017-18/60 | Gottigere Limits to Fortis Hospital | Shifting of Electrical Lines | crore (US$1.0 million) | R.K Associates | 18 May 2018 |
| CEE-1/ELE-US/[R-6, Ph-II]/DPO/2017-18/28 | Fortis Hospital to Jayadeva Circle | Shifting of Electrical Lines | crore (US$1.5 million) | Aravinda Electricals | 08 Sept 2017 |
| CEE(Ele-1)/DPO/0018/R6UG/2017-18/64 | Jayadeva Circle to Dairy Circle | Shifting of Electrical Lines | crore (US$1.0 million) | Aravinda Electricals | 31 Oct 2017 |
| CEE(Ele-1)/DPO/0018/R6UG/2017-18/64 | Dairy Circle to Nagawara | Shifting of Electrical Lines | crore (US$1.1 million) | Gowtham Electricals | 14 Jun 2018 |
| Total | crore (US$4.9 million) | |
| Civil Work |
| Tendering | Section | Length | Successful Bid /Cost | Contractor | Award |
| Phase-2/Reach-6/elevated/Via &Stn/2016/17 | Kalena Agrahara - Dairy Circle | 7.50 km (4.66 mi) | crore (US$68 million) | Simplex Infrastructure | 08 Sept 2017 |
| Reach 6 UG Pkg-1 | Dairy Circle - Langford Town | 3.65 km (2.27 mi) | crore (US$218 million) | Afcons | 06 Nov 2019 |
| Reach 6 UG Pkg-2 | Langford Town - Shivajinagar | 2.76 km (1.71 mi) | crore (US$160 million) | Larsen & Toubro | 28 Feb 2019 |
| Reach 6 UG Pkg-3 | Shivajinagar - Tannery Road | 2.88 km (1.79 mi) | crore (US$150 million) | Larsen & Toubro | 28 Feb 2019 |
| Reach 6 UG Pkg-4 | Tannery Road - Nagawara | 4.59 km (2.85 mi) | crore (US$253 million) | ITD-Cem | 06 Nov 2019 |
| Reach-6/Elevated/Via&Stn/RC/2021/75 | Kalena Agrahara - Dairy Circle | 7.50 km (4.66 mi) | crore (US$43 million) | GR Infraprojects | 03 Aug 2021 |
| Note | Reach 6 Elevated contract awarded to Simplex Infrastructure was cancelled by BMRCL due to poor progress. 37% of the civil work was finished at that time of cancellation. BMRCL later invited new tenders to finish the remaining civil work, which was then awarded to GR Infraprojects. |
| Total | 21.25 km (13.20 mi) | crore (US$770 million) | |
| TVS & E&M |
| Tendering | Section | Length | Successful Bid /Cost | Contractor | Award |
| ECTVS – 01 | TVS, ECS & SCADA | crore (US$24 million) | Blue Star | 02 Jun 2022 |
| ECTVS – 02 | TVS, ECS & SCADA | crore (US$25 million) | UMPESL | 06 Mar 2023 |
| E&M-4/UG & Elev/Ph-II | Electrical & Mechanical | crore (US$22 million) | Blue Star | 25 May 2022 |
| E&M-5/UG/Ph-II | Electrical & Mechanical | crore (US$22 million) | Blue Star | 30 Nov 2022 |
| Total | crore (US$93 million) | |
| Station Work |
| Tendering | Section | Length | Successful Bid /Cost | Contractor | Award |
| Phase II/ICB No. 4 ELEV-DM | Elevators | Kalena Agrahara to Tavarekere | crore (US$790,000) | Johnson Lifts | 03 Feb 2021 |
| Phase II/ICB No.7 ESCAL - DM | Elevated Station Escalators | Dairy Circle - Nagawara | crore (US$3.8 million) | Schindler India | 2 June 2021 |
| Phase-II/5 ELEV-DM | Elevators | Dairy Circle - Nagawara | crore (US$1.6 million) | Johnson Lifts | 19 Aug 2022 |
| R6-Elevated/Arch. Works/STN/2022/87 | Architectural Finishing Works | Kalena Agrahara to Tavarekere | crore (US$6.4 million) | Mysore Light & Interiors | 11 Aug 2022 |
| Bal Arch. Wks/RT01 & RT02/R6-UG/2025/124 | Architectural Finishing Works | Cantonment - Nagawara | crore (US$2.8 million) | DC Facility Management | 23 May 2025 |
| Bal Arch. Wks/RT01 & RT02/R6-UG/2025/125 | Architectural Finishing Works | Dairy Circle - Shivajinagar | crore (US$3.2 million) | ANU Constructions | 23 May 2025 |
| Total | crore (US$19 million) | |
| Miscellaneous |
| Tendering | Section | Length | Successful Bid /Cost | Contractor | Award |
| Phase II/ICB No.EP4-CC | 750V DC Third Rail electrification | crore (US$19 million) | Linxon India | 06 Feb 2021 |
| Reach-6/KOTHNURDEPOT/2019/58 | Kothanur Depot | crore (US$18 million) | ISGEC Heavy Engineering | 9 July 2020 |
| 60E1 880 Grade Rails/RT01/2020/68 | Track Work | crore (US$2.4 million) | Jindal Steel | 12 Jan 2021 |
| 5RS-DM | Rolling Stock (96 Coaches) | crore (US$110 million) | BEML | 08 Aug 2023 |
| Rolling Stock (42 Coaches) | crore (US$48 million) | BEML | 29 Mar 2025 |
| S&T-DM | CBTC signaling & Platform Screen Door | crore (US$36 million) | Alstom Transport | 12 Jun 2024 |
| CEE/ELE/SL/R6/PH-II/2019-20/DPO/134/231 | LED Street Lights,Control Switches,Cables | crore (US$360,000) | Basavashree Electricals | 16 Sept 2019 |
| Reach-6/Road work/2020/67 | Road, Drain, Footpath development works | crore (US$950,000) | M R Pro Tech | 20 Nov 2020 |
| Total | crore (US$240 million) | |
| Total Cost | 21.25 km (13.20 mi) | crore (US$1.1 billion) | |